The flooring appeared to be nailed, however my current neighbor is a retired contractor and mentioned we could go over on a Sunday morning and sink screws into the floor after they had put it in. It seemed fine before, however with the construction glue, would that still be alright to go back and do after the fact?
The request for the first layer of sheetrock to be mudded was advice given to me, that if it is not, it won't be any more effective than just a single layer if both layers aren't mudded. Is this true? I was also told the second layer should be a different thickness to help break up the waves, as if they are the same thickness, it will almost act as just one layer is up and not really help with the transfer of sound. I haven't seen the drywall yet, however I would assume they nail the drywall rather than screw it - that is how most I have seen appear. Not sure about us coming in after the fact and screwing it in, as it will have to be re-mudded again...
again - any thoughts or advice greatly appreciated. Once we have all the "basics" down, I will compose an email stating my wishes on the construction of this room...
good tip to ensure the electrician knows the room will be double rocked to set the boxes at the correct depth.
The main electrical panel will be in the basement, hopefully somewhat centrally located... if that is the case, I assume I will need about a 20-30 ft. run of romex for each duplex...
The request for the first layer of sheetrock to be mudded was advice given to me, that if it is not, it won't be any more effective than just a single layer if both layers aren't mudded. Is this true? I was also told the second layer should be a different thickness to help break up the waves, as if they are the same thickness, it will almost act as just one layer is up and not really help with the transfer of sound. I haven't seen the drywall yet, however I would assume they nail the drywall rather than screw it - that is how most I have seen appear. Not sure about us coming in after the fact and screwing it in, as it will have to be re-mudded again...
again - any thoughts or advice greatly appreciated. Once we have all the "basics" down, I will compose an email stating my wishes on the construction of this room...
good tip to ensure the electrician knows the room will be double rocked to set the boxes at the correct depth.
The main electrical panel will be in the basement, hopefully somewhat centrally located... if that is the case, I assume I will need about a 20-30 ft. run of romex for each duplex...